01 · Sonoma County Airport · construction
Terminal modernization, while flights continued
A terminal project of about $40 million changed passenger routes and contractor access in phases, including during COVID. My job was operational and security coordination. I did not manage the construction budget or the build.
Commercial flights kept operating. The modernized terminal opened in 2022.
Read the account of the terminal work
The situation
Construction moved passenger routes, work areas, and contractor access while the airport was still running commercial flights. COVID added another set of daily constraints.
What I was responsible for
I connected airport staff, contractors, and the security rules. The project outcome is shared. My part was the coordination below.
- Coordinated passenger routes and contractor access as the phases changed.
- Worked with staff, contractors, airlines, and TSA on holdroom access and passenger flow.
- Adjusted daily arrangements for safety and COVID conditions.
- Prepared Airport Security Program amendments and changed-conditions documents for TSA review, including diagrams.
- Oversaw contractor badging and access training.
What came of it
Flights continued through the work. The terminal opened in 2022. The dollar figure is the size of the project I supported.
Photograph: 2022 opening, County of Sonoma CAO Communications.